Contract No. CV/2022/03: Reconstruction of Leung Shuen Wan Pier, Sham Chung Pier and Sam Mun Tsai Village Pier
Contract Overview
The works include the reconstruction of the Leung Shuen Wan Pier with access ramp and reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform, and provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier.

Leung Shuen Wan Pier

Sham Chung Pier

Sam Mun Tsai Village Pier
Description
• Reconstruction of the Leung Shuen Wan Pier with access ramp;
• Reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform;
• Provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier;
• Provision of temporary berthing and mooring facilities during construction stage at each site; and
• Environmental mitigation, monitoring and audit for the works at each site.
8 August 2022
2025
HK$211.07M
Mott MacDonald Hong Kong Limited
Kat Yue Construction Engineering Limited
Leung Shuen Wan Pier

Old Leung Shuen Wan Pier (demolished)
February 2025
Cast in-situ concreting works (completed)
Next activity: Installation of roof cover
Tentative completion of installation of roof cover : 2nd Quarter of 2025
Sham Chung Pier

Old Sham Chung Pier (demolished)
February 2025
Precast unit installation works (completed)
Cast in-situ concreting works (in progress)
Tentative completion of cast in-site concreting works : 1st Quarter of 2025
Sam Mun Tsai Village Pier

Old Sam Mun Tsai Village Pier (modification work in progress)
February 2025
Cast in-situ concreting works (completed)
Installation of roof cover (in progress)
Tentative completion of Installation of roof cover : 1st Quarter of 2025