Works Contract


Contract No. CV/2022/03: Reconstruction of Leung Shuen Wan Pier, Sham Chung Pier and Sam Mun Tsai Village Pier




Contract Overview
The works include the reconstruction of the Leung Shuen Wan Pier with access ramp and reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform, and provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier.

Leung Shuen Wan Pier

Sham Chung Pier

Sam Mun Tsai Village Pier

Description

Contract No.
CV/2022/03
Scope

• Reconstruction of the Leung Shuen Wan Pier with access ramp;
• Reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform;
• Provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier;
• Provision of temporary berthing and mooring facilities during construction stage at each site; and
• Environmental mitigation, monitoring and audit for the works at each site.

Commencement Date

8 August 2022

Tentative Completion Date

2025

Contract Sum

HK$211.07M

Consultant

Mott MacDonald Hong Kong Limited

Contractor

Kat Yue Construction Engineering Limited

Leung Shuen Wan Pier

Old Leung Shuen Wan Pier (demolished)

October 2024
Precast unit installation works (competed)
Cast in-situ concreting works (in progress)
Tentative completion of cast in-situ concreting works: 4th Quarter of 2024

Sham Chung Pier

Old Sham Chung Pier (demolished)

October 2024
Piling works at Sham Chung Pier (completed)
Precast unit installation works (in progress)
Tentative completion of precast unit installation works: 4th Quarter of 2024

Sam Mun Tsai Village Pier

Old Sam Mun Tsai Village Pier (modification work in progress)

October 2024
Precast unit installation works (completed)
Cast in-situ concreting works (in progress)
Tentative completion of cast in-situ concreting works: 4th Quarter of 2024